In late 2025 the fisheries office of Aceh Barat Daya, a district on the west coast of Aceh at the northern tip of Sumatra, paid Rp469 million (about US$29,000) to dig out the mouth of the small fishing harbour at Lhok Pawoh. The contractor finished in five weeks. A few days after its excavator left, the mouth was shallow again [8].
A local legal-aid foundation that went to look said an earlier job, costing about Rp200 million, had lasted longer. “Now the budget is Rp469 million, but within a few days it is shallow again,” its chairman told the national news agency ANTARA [8].
On this one documented job, at least, the office is paying more and getting less.
This article asks why, and whether a new company could take the same money and give the office what it actually wants: a harbour mouth that boats can use for months, not days. Our answer is that the money is real and so is the failure, but the business works only if the offices change what they ask contractors to deliver.
What the district is buying
Many of Aceh’s fishing villages sit where a river meets the sea. Boats leave from a sheltered basin and pass through the river mouth to open water. Waves and floods push sand and stones into that mouth, and at low tide the boats run aground. “When the water is low our boats get stuck. We have to wait for high tide to go out,” one Lhok Pawoh fisherman told the local site AcehGround [9].
Clearing the mouth is called dredging: digging sand and rock out of the channel and the basin so boats can pass. The fishermen use the mouth but do not pay for it. The district fisheries office (DKP) pays, from public money, because the harbour is public infrastructure [7] [8].
This is not one harbour’s problem. Aceh had about 96 fishing ports in 2024, more than any other Indonesian province [12], and many of them sit at river mouths.
How a dredging job is bought today
The office buys each job as a one-off package through the government’s online tender system, where firms submit sealed bids. For Lhok Pawoh it set an estimated price of Rp500 million [7]. Local construction firms bid, and the cheapest acceptable bid usually wins.
The winner was a local firm, CV Kuta Makmur Perkasa [8]. When AcehGround asked the person in charge about the work, he said his company had “only been borrowed for administration” and sent questions to the people doing the work on site [9]. The licensed name won the tender; someone else did the digging.
The office then checks the job by measuring how much material was moved, in cubic metres. The foundation said officials and the contractor signed the handover while work was still going on, “to find a way for the volume to be enough. But what is the use of enough volume if fishermen cannot pass?” [8]
The work also left the hardest part undone. A large rock at the mouth, the thing that most blocked the current and the boats, was left in place. AcehGround reported that the contract was changed partway through: the money meant for lifting the rock went into digging more sand inside the basin instead, so the rock stayed [9].
At a separate Rp900 million river job, paid for by the provincial irrigation agency in Aceh Selatan, residents complained that the dug material was piled on the bank, where heavy rain would wash it back in [10].
How a harbour-mouth dredging job works today
- 1. District office tenders
Fisheries office sets an estimated price of Rp500 million - 2. Cheapest bid wins
A local firm whose name was lent for the paperwork - 3. One ordinary excavator
Five weeks of digging; the large rock stays - 4. Handover on volume
Cubic metres counted; depth not measured - 5. Mouth silts again
Shallow within days; boats wait for the tide - 6. Office pays again
Another package in a later year
Why nobody inside the system fixes it
Everyone involved is behaving sensibly given the rules. The office has an annual budget and must spend it on a tender that auditors will accept. Cubic metres are easy to count and defend; depth that lasts is not in the contract at all.
So the contractor’s best move is to do the minimum that passes the count. Under lowest-price buying, the cheapest way to win is to rent one ordinary excavator for a few weeks, move the contracted volume, and leave. Removing a large rock or carrying spoil away costs extra and earns nothing extra.
As far as the evidence shows, the cause of the problem fits in one sentence: the office pays for volume moved at the lowest price, nobody measures whether boats can pass, and so the depth disappears and the office pays again.
We cannot rule out that some mouths simply refill fast whatever is done. The earlier, cheaper job that lasted longer is weak evidence that how the work is done matters [8], but nobody has measured it.
The other ways a mouth gets cleared
The office’s alternatives are limited. After floods in late 2025, the national public works ministry launched a programme to clear river mouths across Aceh with long-arm and amphibious excavators [2]. By November 2026 it had finished about two of its 23 targeted mouths, and officials said it needs at least three years [1]. Its contractors work on rivers the ministry’s river agency is responsible for, such as Krueng Meureudu [3] [4], not on every village harbour.
A few mouths get cleared for free, by the army or by companies doing charity work. An army task force dredged the Peunaga mouth in Aceh Tamiang [6], and a volunteer team from a large business group, Jhonlin Group, brought a cutter-suction dredger there too [14]. These help only the sites they choose.
Large dredging companies exist, but they work on ports and shipping channels; we found none doing small Aceh harbour jobs. One national firm, Amphibious Indonesia, advertises amphibious dredging machines for “rivers, estuaries and coasts” across Indonesia [15]; we found no Aceh project of theirs.
For a district office, then, the real alternative to a better contractor is the same cheap package again, or waiting for the tide.
Depth-Verified Dredge Execution: what the company would do
The business we examine, which we call Depth-Verified Dredge Execution, would compete in the same tenders as the local firms, for the same budgets. The difference is what the office would receive at the end: a survey showing how deep the channel is, not just a volume.
Suppose the Aceh Barat Daya office tenders another Rp500 million mouth package. Here is how one job would go.
- The company bids about Rp450 million, as a licensed contractor or in partnership with one, and posts the usual bonds: guarantees, usually from a bank or insurer, that it will finish the job or pay a penalty.
- Before digging, a survey partner measures the mouth with an echo-sounder, a boat-mounted device that maps the bottom.
- The company’s resident crew brings a long-arm or amphibious excavator, one that can reach out from the bank or float, removes the rock, digs the channel and basin, and puts the spoil where the current will not carry it back.
- The survey partner measures again, and the company hands the office a before-and-after depth chart alongside the usual volume count.
- The crew moves a day or two along the coast to the next mouth package. Between district jobs, it hires its machine and crew to the ministry’s flood-programme contractors, which will need such equipment for the next few years [1] [2].
Why would the office pick this bid over a cheaper one? Today it cannot, unless it writes depth into the specification; under lowest-price rules, a cheaper volume-only bid wins. So the company’s central ask would be this: show the office a priced offer with a depth requirement, and ask it to tender the next package that way.
The office would gain a job it can defend to auditors, fishermen and the press, and, if the depth lasts, fewer repeat packages. Whether office heads and the tender committees that write specifications see enough benefit to change a familiar process is something nobody has asked them.
The local firms would lose. The obvious reply from a well-run one is to rent better machines and copy the survey.
The two numbers that decide it
The first is cost: our model puts one five-week job at roughly Rp300–410 million, against the Rp469 million the office paid at Lhok Pawoh [8]. That cost includes the survey and the long-arm machine, so a bid of about Rp450 million leaves a margin in most cases.
Only two of the seven cost lines come from a source: excavator hire, which a Bali rental firm lists at Rp395,000 an hour with operator and fuel [13], and labour at Banda Aceh’s official rate [11]. The rest are our assumptions: the long-arm machine, moving equipment to the site, the survey, lifting rock and carrying spoil, and the cost of bidding and waiting between jobs.
What one five-week job might cost, against what the office paid
The weakest line is the long-arm machine’s rent. We found no Aceh rental price for a long-arm or amphibious excavator, and we assumed Rp80–120 million for five weeks. Everything else in the expensive case adds up to about Rp290 million. So if the machine costs more than about Rp170 million, that case costs more than the Rp469 million the office paid, and the job loses money.
The second number is how busy the crew stays: it needs at least five jobs a year to cover its fixed costs. Some of those can be hire work for the flood programme, but the business still has to win somewhere between four and twelve district packages a year across Aceh.
On our rough count, Aceh’s district harbour mouths might add up to Rp5–36 billion a year of dredging, if half to most of the 96 ports need a job every one or two years. A company winning a handful of those could earn about Rp1–6 billion a year. That supports a small crew, not a large firm, unless the offices move to longer contracts or the company expands to North Sumatra.
Could it work?
The budget exists and the failure is documented, so a company that delivers lasting depth would be selling something the offices already pay for and do not get. But it can only win if an office agrees to buy depth instead of volume; otherwise the cheaper volume bid wins every time. And it only matters if properly dredged mouths stay open for months rather than days, which nobody has measured.
The cheapest first step is to show three west-coast fisheries offices a priced offer with a depth requirement and ask whether they will tender the next package on it. If the answer is yes, a larger prize follows: a contract to keep one mouth open for a whole season, which we call the Seasonal Depth Maintenance Contract, if district rules allow it.
What has to be true
The business described above stands on these claims, listed in the order we would test them.
- Kabupaten DKPs and their procurement working groups will write surveyed navigable depth into mouth-dredging specifications, or otherwise reward it, at roughly today’s package budget
Not yet tested · DKP and Pokja
Lhok Pawoh acceptance focused on volume; a local NGO publicly asked DKP to check before paying [8] [8]
Would break if: DKPs will tender only on volume and lowest price
Cheapest test: Show three west-coast DKPs a priced offer with a depth specification and ask for written agreement to use it in the next tender - A properly executed campaign, with rock removed and spoil placed away from the channel, keeps a mouth navigable for at least one season
Not yet tested · Fishermen and DKP
An earlier Rp200 million campaign at Lhok Pawoh reportedly lasted longer [8]; rock left at the mouth was blamed [9] [8] [9]
Would break if: Surveys show depth lost within weeks even after proper work
Cheapest test: Monthly depth survey of one mouth for three months after a properly executed campaign - A long-arm or amphibious machine can be leased in Aceh for under about Rp170 million per 35-day campaign
Not yet tested · Equipment lessors
No Aceh rate found; standard excavator hire is listed at Rp395,000 an hour in Bali [13] [13]
Would break if: Written quotes exceed about Rp170 million per campaign
Cheapest test: Written lease quotes from an amphibious equipment specialist and two Medan lessors - A new firm can win 4-12 Aceh mouth packages a year in lowest-price LPSE tenders at a positive margin
Our inference from the sources · Pokja / tender market
Package budgets of Rp200-500 million exist [7][8]; win rates are assumed [7] [8]
Would break if: LPSE history shows fewer than about 20 mouth packages a year across Aceh, or winning bids far below the modelled cost
Cheapest test: Count Aceh mouth and basin dredging packages and winning bids on LPSE for 2023-2026 - DKPs pay within the fiscal year so a small contractor’s working capital survives late-year awards
Not yet tested · DKP
Would break if: Payments slip past the fiscal year routinely
Cheapest test: Ask two contractors who completed DKP packages when they were paid
Research Notes
The sources, calculations and evidence records behind this investigation. Numbered citations in the article link here; ↩ returns to the text.
How we sized and costed the business
All figures are per campaign, meaning one five-week job at one harbour mouth of about the Lhok Pawoh size. “Sourced” means taken from a cited source; “assumed” means our own estimate.
| Item | Calculation | Status |
|---|---|---|
| Price the office paid | Rp 469 million (estimated price Rp 500 million; budget ceiling Rp 476 million) | Sourced [7] [8] |
| Standard excavator | Rp 395,000 an hour × about 280 hours (35 days × 8 hours) ≈ Rp 111 million, operator and fuel included | Sourced rate, Bali list price [13]; hours assumed |
| Labour | Rp 39,750 a shift × about 300 shifts ≈ Rp 12 million | Sourced rate, Banda Aceh 2025 [11]; shifts assumed |
| Long-arm or amphibious machine | Rp 80–120 million for 35 days | Assumed; no Aceh rate found |
| Moving equipment to site | Rp 10–20 million, shared between nearby mouths | Assumed |
| Depth survey before and after | Rp 25–40 million | Assumed |
| Lifting rock and placing spoil | Rp 30–60 million | Assumed |
| Bids, bonds and idle days | Rp 30–50 million | Assumed |
| Total cost | Rp 298 million (low) to Rp 413 million (high) | Estimate |
| Margin at the Lhok Pawoh price | Rp 469 million − Rp 298–413 million ≈ Rp 55–170 million | Estimate |
| Break-even rent for the long-arm machine | Rp 469 million − (Rp 413 million − Rp 120 million) ≈ Rp 176 million, rounded to about Rp 170 million | Estimate |
For comparison, a 2025 cost estimate for dredging two reservoirs in North Sumatra with a cutter-suction dredger, using the public works ministry’s standard unit prices, came to about Rp 147,000–235,000 per cubic metre including buying the equipment [5]. It is a different kind of job and we did not use it in the model.
The first market.
| Step | Calculation | Status |
|---|---|---|
| Fishing ports in Aceh, 2024 | 18.32 % of 524 ≈ 96 | Sourced [12] |
| Share at silting river mouths | 50–80 % | Assumed |
| Campaigns per port per year | 0.5–1 | Assumed |
| Value per campaign | Rp 0.2–0.47 billion | Sourced range [8] |
| Annual spending on mouth campaigns | 96 × 50 % × 0.5 × Rp 0.2 billion ≈ Rp 4.8 billion; 96 × 80 % × 1 × Rp 0.47 billion ≈ Rp 36 billion | Estimate |
| What one firm could earn in year 2 | 4–12 campaigns × Rp 0.3–0.47 billion ≈ Rp 1.2–5.6 billion, plus perhaps Rp 1–3 billion of hire to flood-programme contractors | Assumed win rate and hire |
The weakest inputs are the rent of the long-arm machine and how many packages a new firm could win. The count of district mouth packages on the tender system for 2023–2026 has not been made; it is the cheapest way to replace the assumed share and frequency.
Who else clears harbour mouths
| Who | What they do | Price | In Aceh’s district harbours? |
|---|---|---|---|
| Local contractors (for example CV Kuta Makmur Perkasa, CV Datuk Raja Dewa) | One-off packages Win lowest-price tenders, rent excavators, paid on volume | Rp 469 million at Lhok Pawoh [8]; over Rp 900 million for a 2.8 km river job [10] | Yes [7] [9] |
| Public works ministry’s river agency and its contractors | Flood programme Rivers, mouths and breakwaters with long-arm and amphibious machines | Not published per package | Yes, on the rivers it is responsible for [2] [3] [4] |
| Army task force (Satgas Kuala) | Free dredging At mouths it selects | Free | Selected sites [6] |
| Jhonlin Group volunteers | Charity dredging Cutter-suction dredger at Kuala Peunaga | Free | One site [14] |
| Amphibious Indonesia | Amphibious machines Advertises river, estuary and coastal dredging nationwide | No published price | Unknown; no Aceh project found [15] |
| PT Pengerukan Indonesia (Rukindo) | Large dredging Ports and shipping channels | Not published | Unknown; no Aceh small-harbour work found (search results only) |
| Doing nothing | Wait for the tide Fishermen time trips to high water | Lost trips and grounded boats | Everywhere [9] |
Searches for a long-arm or amphibious excavator for hire in Aceh, in Indonesian, found no local renter. That shows only that we did not find one.
What is documented and what is not
- Documented: the Lhok Pawoh payment and its quick return to shallow water [8]; acceptance on volume as described by the foundation [8]; the rock left in place and the borrowed company name [9]; spoil piled on the bank at Trumon [10]; the slow progress of the flood programme [1].
- Inferred: that lowest-price, volume-based buying is the general cause across Aceh, not only at these two jobs.
- Unknown: how fast a properly dredged mouth refills; whether any district office would write depth into a specification; the Aceh rent of a long-arm machine.
- Sources disagree on where the Lhok Pawoh money came from: ANTARA says Aceh’s special autonomy fund [8], AcehGround says the district budget [9]. The amount is the same in substance (Rp 469 million; “more than Rp 460 million”).
The two businesses in more detail
Depth-Verified Dredge Execution needs a licensed contractor, or a partnership with one, able to post bonds; a long lease on one long-arm or amphibious machine; a survey partner with an echo-sounder; and working relationships with fisheries offices in several neighbouring districts. Its bid could also offer to hold back part of the payment until a second survey, some weeks later, shows the depth has lasted. Its decisive test: show three west-coast fisheries offices a priced offer with a depth requirement and count how many agree in writing to tender their next package on it, at a budget within 10 % of their last one. None agreeing would stop the idea.
Seasonal Depth Maintenance Contract would follow a verified job: the office pays one fee for a mouth kept at a surveyed depth through the season, with monthly surveys and small touch-up digs. It depends on whether district procurement rules allow a season-long contract judged on depth. Its test is a written question to two districts’ fisheries and procurement offices asking whether such a package can be tendered, with the rule cited.
Routes considered
Folded into Depth-Verified Dredge Execution: a crew that rotates around a cluster of nearby harbours; renting the long-arm machine only for the rock and deep work; placing spoil away from the channel instead of a separate barge service; hiring out the crew and machine to flood-programme contractors between district jobs; and holding back part of the payment until the depth has lasted.
- Paying fishermen to monitor and halt work: no office has the budget or legal power to give fishermen that role, though they remain useful witnesses.
- Selling dredging to fish farms and private port owners: we found no such buyers in Aceh, while the flood programme already needs this equipment.
- Booking dredging before the wet season: this is a timing version of the Seasonal Depth Maintenance Contract and depends on the same rules.
Sources
[1] Katadata, “Jelang Satu Tahun Bencana Aceh, Rekonstruksi Infrastruktur Dasar Tuntas”, 19 November 2026. Read in full. Progress of river and mouth clearing: about two of 23 mouths; at least three years needed. ↩
[2] InfoPublik, “Pemerintah Percepat Normalisasi 38 Muara Sungai di Aceh”, 23 February 2026. Read in full. The government’s river-mouth programme and its equipment. ↩
[3] ANTARA, “BWS siagakan alat berat untuk penanganan darurat banjir se Aceh”, 29 September 2026. Read in full. The river agency’s equipment and reconstruction packages, including mouth dredging and breakwaters. ↩
[4] InfoPublik, “Kementerian PU Percepat Penanganan Banjir Pidie Jaya”, 5 November 2026. Read in full. Krueng Meureudu basin works. ↩
[5] Jurnal Polinema, dredging cost estimate for the Sigura-gura and Tangga reservoirs, Asahan, using 2025 public works unit prices. Results section read. Comparison only.
[6] ANTARA, “Satuan Tugas Kuala keruk sedimentasi muara Peunaga atasi masalah nelayan”, 31 January 2026. Read in full. Free army dredging at a selected mouth. ↩
[7] DataLPSE, tender 10064379000, “Pengerukan Kolam Labuh dan Mulut Muara TPI Lhok Pawoh”. Read in full. Buyer (the district fisheries office), estimated price Rp 500 million and budget ceiling Rp 476 million. ↩
[8] ANTARA Aceh, “SaKA ingatkan DKP Abdya cermat bayar proyek pengerukan muara”, 6 November 2025. Read in full. The Rp 469 million job, the contractor, five weeks of work, shallow again within days, the earlier Rp 200 million job and the handover on volume. ↩
[9] AcehGround, “Proyek Pengerukan Muara Lhok Pawoh Abdya Senilai Rp460 Juta Diduga Asal Jadi, Nelayan Mengeluh”. Read in full. The rock left in place, the contract change, the borrowed company name and the fisherman’s account. It reports anonymous sources; the office did not respond. ↩
[10] Waspada, “Telan Anggaran Rp900 juta, Proyek Normalisasi Sungai Ladang Rimba Trumon Tengah Diduga Asal Jadi”, October 2025. Read in full. Spoil piled on the bank at a provincial river job. ↩
[11] Banda Aceh Mayor’s Regulation No. 11 of 2025, standard unit costs. Relevant table read. Field worker Rp 39,750 a shift. ↩
[12] Statistics Indonesia (BPS), “Statistik Pelabuhan Perikanan 2024”, 7 November 2025. Summary read. 524 fishing ports nationally, 18.32 % in Aceh. ↩
[13] CV Jiwa Karya Rental, SANY SY75C excavator rental, Bali. Read in full. A seller’s list price: Rp 395,000 an hour with operator and fuel. Not an Aceh price. ↩
[14] Metro TV, “Jhonlin Group Keruk Muara Sungai di Aceh Tamiang, Percepat Pemulihan Ekonomi Nelayan”, 28 February 2026. Read in full. Volunteer dredging at Kuala Peunaga. ↩
[15] Amphibious Indonesia, home page. Read in full. The company’s own claims about its equipment and coverage. ↩